MBI Timelines 2024 Update
Building on previous Environmental Policy Innovation Center (EPIC) | Ecological Restoration Business Association research from 2023 (here and here), EPIC analyzed new US Army Corps of Engineers (Corps) data to see if timelines on mitigation banks were meeting the federally mandated approval time limit of 225 days.
Federal Processing Time Continues to Exceed 225 Days
The study found that the average project took 1.5x longer than required “on the regulator’s desk.” Mandatory federal processing of a mitigation bank instrument takes 336 days on average - 1.5 times longer than required in regulations. There is a decrease in average federal processing of 17 days when we isolate the new data from 2022-2023, however this is not a statistically significant trend.
Sponsor, Additional, and Total Processing Times Are Increasing
The full timeline for project approval - including back and forth between the Corps and applicants - takes an average of 1149-1195 days, an increase of 51-97 days from the previous analysis. The range reflects analyzing the data with and without some dubious data records.
Additionally, the study revealed a statistically significant trend of an additional 18-27 days being added to the total approval timeline each year, and 15-17 days for sponsor processing.
New Corps Guidance
Timeline Compliance: USACE reaffirmed its commitment to the 2008 regulations, emphasizing the importance of adhering to established timelines for wetland and stream mitigation projects.
Streamlining Interagency Review: The guidance stresses that reviews by multiple agencies should not create process bottlenecks, echoing EPIC's recommendations to improve the Interagency Review Team (IRT) process.
Focus on Ecological Performance: USACE is shifting focus towards achievable ecological outcomes rather than worrying over “the perfect plan,” potentially addressing some of the delays identified in the study.
Standardization of Processes: The development of national and district-level templates for various aspects of the approval process aims to increase consistency and predictability, addressing district-level variations highlighted in the report.
Study the Causes of Delays: While EPIC’s research quantified delays in the process, Corps headquarters is committing to investigating underlying causes.
It's encouraging to see Corps leadership taking steps that align with our research findings. The new guidance addresses many of the bottlenecks we've identified and could significantly improve the efficiency of the mitigation bank approval process. While the changes announced by the Corps are promising, their implementation and impact will need to be monitored over time. EPIC will use this research as a baseline to track whether the Corps guidance has an effect in future studies.
Resources
Link to full report: The Time It Takes for Restoration 2024 Update
Previous 2023 EPIC | ERBA quantitative analysis of MBI timelines: The Time it Takes for Restoration: An Analysis of Mitigation Banking Instrument Timelines (2023)
Pervious 2023 EPIC | ERBA qualitative analysis of bottlenecks and solutions: The Time it Takes for Restoration: A Qualitative Analysis of Factors that Speed and Slow Mitigation Banking Approval Timelines (2023)
The Restoration Economy Center, housed in the national nonprofit Environmental Policy Innovation Center (EPIC), aims to increase the scale and speed of high-quality, equitable restoration outcomes through policy change. Email becca@policyinnovation.org if interested in learning more, sign up for our newsletter, or consider supporting us!